TVATennessee Valley Authority / Memphis Light Gas & Water★ from research vault

Memphis — xAI Colossus (TVA)

Memphis (Southwest) · DeSoto County MS

The high-realization outlier. xAI self-supplies with on-site gas turbines plus ~250 MW from TVA (+150 MW approved), so it actually energizes what it requests — ~1 GW+ live in under two years. In January 2026 a third building expanded Colossus to a ~2 GW target (555,000 GPUs, ~$18B), and in March 2026 xAI filed a $659M permit to build out the Colossus 2 (Tulane Road) site, with Solaris JV turbines reaching >1.1 GW by Q2 2027. When you build your own power, the queue isn't the bottleneck.

Gen delivered / qtr
228 MW
DC energized / qtr
200 MW
DC requested / qtr
283 MW
Realization rate
71%
Gen delivery rate
62%
Static queue drain
0.9 yr

Megawatts per quarter — requested vs energized vs delivered

Faint rose = load requested (queue inflow, padded); solid rose = load energized; green = generation delivered (the supply KPI).

Delivered generation (supply)Energized DC load (real)Requested DC load (queue inflow — padded)faded = forecast
’24-Q3’24-Q4’25-Q1’25-Q2’25-Q3’25-Q4’26-Q1’26-Q2’26-Q3’26-Q4

Quarterly throughput

QuarterGen deliveredDC energizedDC requestedRealization
2024-Q3906510065%
2024-Q41209014064%
2025-Q111010017059%
2025-Q215012020060%
2025-Q316014023061%
2025-Q422016027059%
2026-Q125022030073%
2026-Q228028033085%
2026-Q3(f)31034036094%
2026-Q4(f)340400390103%

All figures in MW. (f) = forecast. Realization = energized ÷ requested. Requested is gross queue inflow and is heavily padded — it is not energized load.

Anchor tenants & supply

  • xAI Colossus 1
    Southwest Memphis · ~250 MW grid + on-site gas turbines
    250 MW
    Operating
  • xAI Colossus 2
    Memphis · 3rd building Jan 2026 → ~2 GW target; 555k GPUs; Solaris JV turbines
    2.0 GW
    Energizing
  • TVA supplemental supply
    Grid · Board-approved additional 150 MW
    150 MW
    Approved

Queue snapshot

Generation in queue
8.0 GW
Data-center load requested
800 MW
Data-center share of load
85%
Active projects
41
Typical interconnect wait
3.0 yr

Sources