InterconnectMonitor
← All regions
Southeast (non-ISO)Georgia Power

Georgia — Metro Atlanta (Southern Co.)

Atlanta · Douglas County · Social Circle

Georgia Power's prospective large-load pipeline — ~80% data centers — ballooned to ~69 GW (part of a ~75 GW Southern-wide pipeline). As of Q1 2026 earnings ~11 GW now sits under executed contracts (28 large-load projects), up from ~1.9 GW a year earlier, even as PSC staff warn data centers are "underperforming expectations" on materialization. In December 2025 the PSC approved 9,885 MW of new resources (~two-thirds gas, rest BESS/renewables) to serve it. Vogtle's new nuclear units provide rare carbon-free baseload in a vertically-integrated, non-ISO market — so the slice that does get built realizes faster than the ISO megamarkets.

Gen delivered / qtr
480 MW
DC energized / qtr
275 MW
DC requested / qtr
2.9 GW
Realization rate
9%
Gen delivery rate
52%
Static queue drain
35.9 yr

Megawatts per quarter — requested vs energized vs delivered

Faint rose = load requested (queue inflow, padded); solid rose = load energized; green = generation delivered (the supply KPI).

Delivered generation (supply)Energized DC load (real)Requested DC load (queue inflow — padded)faded = forecast
’24-Q3’24-Q4’25-Q1’25-Q2’25-Q3’25-Q4’26-Q1’26-Q2’26-Q3’26-Q4

Quarterly throughput

QuarterGen deliveredDC energizedDC requestedRealization
2024-Q32001401,00014%
2024-Q43201701,30013%
2025-Q12801901,65012%
2025-Q23802102,00011%
2025-Q33602302,40010%
2025-Q44802602,9009%
2026-Q15202903,1009%
2026-Q25603203,30010%
2026-Q3(f)6003503,20011%
2026-Q4(f)6403803,30012%

All figures in MW. (f) = forecast. Realization = energized ÷ requested. Requested is gross queue inflow and is heavily padded — it is not energized load.

Anchor tenants & supply

  • Microsoft
    Atlanta / Douglas County
    900 MW
    Energizing
  • Google
    Douglas County
    700 MW
    Operating
  • QTS
    Fayetteville / Atlanta
    1.1 GW
    Approved

Queue snapshot

Generation in queue
18 GW
Data-center load requested
69 GW
Data-center share of load
80%
Active projects
124
Typical interconnect wait
3.5 yr

Sources