PJMAEP Ohio

Central Ohio — Columbus / New Albany (PJM)

New Albany · Columbus · Hilliard

Central Ohio went from ~0.6 GW metered DC load (2024) to 17,861 MW of contracted data-center load (Feb 2026) — of which 5,642 MW was signed under the new tariff and 12,219 MW before it — against requests that once topped 30 GW. PUCO's 85% data-center tariff (Case 24-508) exists specifically to discipline a padded forecast, and it is working.

Gen delivered / qtr
385 MW
DC energized / qtr
245 MW
DC requested / qtr
3.7 GW
Realization rate
7%
Gen delivery rate
46%
Static queue drain
19.5 yr

Megawatts per quarter — requested vs energized vs delivered

Faint rose = load requested (queue inflow, padded); solid rose = load energized; green = generation delivered (the supply KPI).

Delivered generation (supply)Energized DC load (real)Requested DC load (queue inflow — padded)faded = forecast
’24-Q3’24-Q4’25-Q1’25-Q2’25-Q3’25-Q4’26-Q1’26-Q2’26-Q3’26-Q4

Quarterly throughput

QuarterGen deliveredDC energizedDC requestedRealization
2024-Q31501201,3009%
2024-Q42601501,7009%
2025-Q12201602,1008%
2025-Q23001802,6007%
2025-Q32802003,1006%
2025-Q43802303,7006%
2026-Q14202603,9007%
2026-Q24602904,1007%
2026-Q3(f)5003204,3007%
2026-Q4(f)5403504,5008%

All figures in MW. (f) = forecast. Realization = energized ÷ requested. Requested is gross queue inflow and is heavily padded — it is not energized load.

Anchor tenants & supply

  • Amazon Web Services
    New Albany
    1.4 GW
    Operating
  • Google
    New Albany / Lancaster
    900 MW
    Energizing
  • Microsoft
    Central Ohio
    800 MW
    Approved
  • Meta
    New Albany
    700 MW
    Permitting

Queue snapshot

Generation in queue
20 GW
Data-center load requested
30 GW
Data-center share of load
90%
Active projects
205
Typical interconnect wait
5.0 yr

Sources