PJMDominion Energy Virginia★ from research vault

Northern Virginia — “Data Center Alley”

Loudoun County · Prince William · Richmond

The densest data-center market on earth. Dominion's ~70 GW SCC request queue (only ~25 GW with connection dates) and ~51 GW of contracted data-center capacity across the SELOA/CLOA/ESA stages as of March 2026 (Q1 2026 earnings, up ~5% from December and triple mid-2023's 16.5 GW) dwarf the ~4 GW data-center coincident peak actually energized — a ~5-6% realization rate. The GS-5 large-load rate class (85% minimum demand, 14-year contracts, effective Jan 2027) disciplines the padding, and in July 2026 the SCC took up whether to shift more transmission cost onto data centers via Rider T-1. The pipeline is enormous; the meter moves slowly.

Gen delivered / qtr
885 MW
DC energized / qtr
190 MW
DC requested / qtr
4.3 GW
Realization rate
4%
Gen delivery rate
41%
Static queue drain
19.8 yr

Megawatts per quarter — requested vs energized vs delivered

Faint rose = load requested (queue inflow, padded); solid rose = load energized; green = generation delivered (the supply KPI).

Delivered generation (supply)Energized DC load (real)Requested DC load (queue inflow — padded)faded = forecast
’24-Q3’24-Q4’25-Q1’25-Q2’25-Q3’25-Q4’26-Q1’26-Q2’26-Q3’26-Q4

Quarterly throughput

QuarterGen deliveredDC energizedDC requestedRealization
2024-Q33801402,4006%
2024-Q46901502,6006%
2025-Q15401502,9005%
2025-Q27201603,3005%
2025-Q36101703,7005%
2025-Q48801804,2004%
2026-Q19502004,5004%
2026-Q21,1002104,8004%
2026-Q3(f)1,2502305,1005%
2026-Q4(f)1,4002505,4005%

All figures in MW. (f) = forecast. Realization = energized ÷ requested. Requested is gross queue inflow and is heavily padded — it is not energized load.

Anchor tenants & supply

  • Amazon Web Services
    Loudoun / PW County · Largest single occupant of the zone
    4.8 GW
    Operating
  • Microsoft
    Loudoun County
    2.2 GW
    Energizing
  • Google
    Loudoun County
    1.4 GW
    Approved
  • QTS / Digital Realty
    Prince William
    1.9 GW
    Permitting

Queue snapshot

Generation in queue
46 GW
Data-center load requested
70 GW
Data-center share of load
92%
Active projects
612
Typical interconnect wait
5.5 yr

Sources