Louisiana — Meta Richland Parish (MISO)
Richland Parish · Holly Ridge · Baton Rouge
The “all pipeline, nothing energized yet” extreme. Meta's Hyperion campus — now projected at $200B+ and up to 9-10 buildings (~5 GW of compute) — is under construction but not operational until ~2030. To power it Entergy is building 10 gas plants totaling ~7.5 GW (a March 2026 deal added seven units on top of the original three; ~$11B, Meta-funded, plus up to 2.5 GW of renewables/storage). The LPSC voted April 15, 2026 to fast-track the application with a final decision due December 2026; in July 2026 an administrative law judge ordered Meta to disclose withheld evidence behind the gas buildout. Massive requested load, essentially zero on the meter today.
Megawatts per quarter — requested vs energized vs delivered
Faint rose = load requested (queue inflow, padded); solid rose = load energized; green = generation delivered (the supply KPI).
Quarterly throughput
| Quarter | Gen delivered | DC energized | DC requested | Realization |
|---|---|---|---|---|
| 2024-Q3 | 240 | 0 | 900 | 0% |
| 2024-Q4 | 360 | 0 | 1,300 | 0% |
| 2025-Q1 | 320 | 0 | 1,700 | 0% |
| 2025-Q2 | 420 | 10 | 2,100 | 0% |
| 2025-Q3 | 400 | 10 | 2,500 | 0% |
| 2025-Q4 | 540 | 10 | 3,000 | 0% |
| 2026-Q1 | 600 | 20 | 3,200 | 1% |
| 2026-Q2 | 660 | 30 | 3,400 | 1% |
| 2026-Q3(f) | 720 | 40 | 3,600 | 1% |
| 2026-Q4(f) | 780 | 50 | 3,800 | 1% |
All figures in MW. (f) = forecast. Realization = energized ÷ requested. Requested is gross queue inflow and is heavily padded — it is not energized load.
Anchor tenants & supply
- Meta “Hyperion”Richland Parish · $200B+; ~5 GW compute; operational ~20305.0 GWPermitting
- Entergy gas fleet (gen)Richland Parish · 10 plants / ~7.5 GW, ~$11B Meta-funded; LPSC decision Dec 2026; online 2028-307.5 GWApproved
Queue snapshot
- Generation in queue
- 25 GW
- Data-center load requested
- 14 GW
- Data-center share of load
- 80%
- Active projects
- 190
- Typical interconnect wait
- 4.5 yr
Sources
- Fortune — Meta orders 10 gas plants (7.5 GW) for Hyperion, triple initial plans (Mar 2026) ↗
- DCD — Entergy approved to build three gas facilities for Meta's 2GW LA data center ↗
- NOLA — Louisiana regulators advance Meta/Entergy power expansion ↗
- UCS — Judge orders Meta to reveal withheld evidence behind Louisiana gas buildout (July 2026) ↗